Two Lakes : Dreams Realized

 

Computations

 

Highway 80  Gage
Historical Peaks
Bridges
Weirs
HEC-2 Computer Model
The Golder Evaluation

 

CONSIDERATIONS AND COMPUTATIONS FOR
FLOOD CONTROL LAKE
IN JACKSON MISSISSIPPI

     For conceptual purposes, while studying the feasibility of using a lake through Jackson for Flood control our initial calculations were made using an average Pearl River cross section.

handdrawing_pg11.gif (13139 bytes) 

And the Chezy-Manning Hydraulic Equation:

Q = AV
V= C (rs)1/2
r = A/p
s = h/l
Where:
Q = Flow rate (ft3/sec)
A = Cross sectional area (ft2)
V = Velocity (ft/sec)
r = Hydraulic radius (ft)
p = Wetted perimeter (ft)
s = Slope of water surface (ft/ft)
l = Distance (ft)
h = Drop in water level (ft)
C is found using the kutter formula

C = 41.6 + 1.1811/n + 0.000281/s
       1 + (41.6 + 0.00281/s) n/(r)1/2

Where:
n = Manning roughness coefficient

     This was much less cumbersome than using the HEC-2 program with its many cross sections and data points. This way we could get a feel for what it would take by simply changing a few numbers. This would get us in the ball park of what it would take and later we could use a more accepted computer model.

 

Present Condition

     The first step was to take historical flood levels vs flow rates and generate a pre-downtown levee/structure curve and a post levee/structure curve.

fc_chart_pg12.gif (6618 bytes)

     When plotting the Pearl River Jackson Gage data of pre 1963 annual flows and post 1969 annual peak flows, one must go back to the period of 1874 - 1935 in order to have any significant amount of flood data which could compare to the 1979 and 1983 floods. By using all of the available yearly peak flow information, excluding the period in which the levees were constructed, and assuming that the information is somewhat accurate, it can clearly be seen that there is a difference in magnitude of the gage readings taken before 1963 compared to those taken after 1969 (approximately 3 feet at this location). It should be noted that the gauge readings were taken downstream of the cutoff channel. All that may be concluded from this information due to the long span of time it covers is that the combination of bridges, levees, landfills and other encroachments (see map on following page) seem to have an increase in water levels for this location for the higher magnitude floods.

 

map_pg14.gif (75979 bytes)

Year

Date

Gage Height (ft-HGVD)

Discharge (cfs)

Notes Year

Date

Gage Height (ft-HGVD)

Discharge (cfs)

Notes
1874 4-25-74 37.00 80000 1 1947 1-22-47 30.66 26000
1881 12-05-80 36.50 70000 1 1948 3-11-48 30.63 25600
1900 4-24-00 36.70 35000 1949 1-12-49 33.11 38300
1901 01 24000 1950 1-14-50 33.90 44700
1902 3-31-02 37.50 85000 1951 4-04-51 34.36 49100
1903 2-14-03 33.70 43600 1952 3-16-52 17.51 6600
1904 4-11-04 11.10 5295 1953 5-09-53 31.65 28500
1905 2-17-05 29.20 24880 1954 5-12-54 23.25 10600
1906 3-29-06 29.80 26000 1955 4-20-55 31.50 27500
1907 10-13-06 30.10 26600 1956 4-14-56 31.78 29300
1908 2-23-08 29.08 26000 1957 4-11-57 30.32 22100
1909 5-30-09 35.30 58300 1958 5-08-58 34.23 38900
1910 4-20-10 16.40 9020 1959 2-20-59 26.52 13600
1911 4-16-11 22.60 14600 1960 3-11-60 30.29 22600
1912 4-23-12 31.70 29600 1961 3-01-61 35.00 46000
1913 3-18-13 29.00 24600 1962 12-21-62 37.24 66100 2 *
1914 4-09-14 31.10 29900 1963 3-19-63 17.74 6440 2 **
1915 2-09-15 26.70 20200 1964 3-23-64 31.00 24000 2
1916 1-09-16 26.70 20200 1965 2-17-65 32.02 28800 2
1917 4-11-17 26.50 19800 1966 2-18-66 30.99 26700 2
1918 5-04-18 22.90 15300 1967 2-25-67 20.16 8130 2
1919 3-19-19 27.60 21800 1968 12-23-67 31.43 29900 2
1920 12-14-19 30.50 28100 1969 4-20-69 34.55 44800 2
1921 4-21-21 32.90 37800 1970 5-03-70 27.43 18300 2
1922 3-11-22 28.80 24200 1971 5-15-71 32.67 32100 2
1923 2-16-23 30.70 28700 1972 1-17-72 32.56 31600 2
1924 3-08-24 26.80 20400 1973 4-19-73 32.99 33400 2
1925 1-25-25 28.80 24200 1974 4-18-74 34.36 40300 2
1926 3-17-26 27.00 20700 1975 3-20-75 32.43 34400 2
1927 2-24-27 30.00 26800 1976 4-03-76 35.74 50400 2
1928 4-30-28 29.80 26300 1977 4-09-77 35.57 48900 2
1929 3-24-29 32.30 30600 1978 5-14-78 31.80 27400 2
1930 5-28-30 31.90 29400 1979 4-17-79 43.28 128000 2,3,4
1931 8-05-31 26.40 15100 1980 4-13-80 35.50 50900
1932 2-28-32 29.10 21300 1981 4-05-81 30.10 24600
1933 12-19-32 35.20 60000 1982 12-02-82 36.00 46600
1934 3-13-34 28.00 18600 1983 5-23-83 39.50 78600
1935 3-12-35 35.18 56700 1984 3-06-84 28.40 20800
1936 2-12-36 32.46 34400 1985 2-07-85 29.00 23800
1937 1-29-37 30.00 22800 1986 11-29-86 29.40 25300
1938 4-09-38 32.07 32100 1987 2-28-87 32.60 39100
1939 2-15-39 28.93 19200 1988 4-03-88 27.70 19700
1940 7-18-40 31.94 30100 1989 1-17-89 30.20 24000
1941 12-29-41 25.17 12700 1990 1-25-90 33.70 38900
1942 3-17-42 19.41 7720 1991 5-05-91 35.00 45500
1943 3-30-43 28.43 19200
1944 4-04-44 34.03 46700
1945 3-01-45 32.58 36900
1946 2-17-46 34.44 49600

1 - Historic peaks outside period of record
2 - Flow regulated since 27 Sep61 by Ross Barnett Reservoir, 15 miles upstream
3 - Estimated discharge of 145,000 cfs used in frequency study to account for flood control regulation at Ross Barnett Dam, 15 miles upstream of gage
4 - Highest peak since 1874

*  - Reservoir constructed
** - Levees constructed

 

     Using the Chezy equation, an average cross section, historical slopes, and flood data friction factors were derived to get this cross section to fit the pre-levee/structure curve at various flow rates.

 

Main Body of Lake

Now a much narrower more efficient cross section (or lake) was derived that would handle the 1979 flood at the safe flood levels assuming the water levels south of the lake would remain the same for either situation.

handdrawing_pg16.gif (16195 bytes)

The cleared and graded lake with 2000 foot wide dredged flow course now has friction factors similar to or better than the original river channel. Various channel depths were used until through iteration the derived water level and hydraulic gradient could be achieved.

From an engineering stand point it could be considered that we are designing a flow course that would have the ability to handle 128,000 cubic feet per second with a rise of about three feet over a length of 11 miles.

 

Bridges

The next question is what to do at the bridges? Most of the Pearl River bridges in Jackson have a span of at least 1000 feet. The Highway 80 bridge for example has a span of 1170 feet.

hwy_dept_bridge_plan.gif (33354 bytes)

If a 1000 feet wide flow course was dredged down to the top of the pile caps over a l000 foot length, the resulting cross section would have the same hydraulic gradient as the rest of the lake.

In the event that any of the bridges are not constructed in a manner that would lend itself to this depth of dredging, side pilings could be driven with a concrete band poured around them and the existing piling tying them all together in order to obtain the proper safety factors. It would also be possible not to dredge as deep directly under the bridge. Limestone could then be added to prevent washing. The area under the bridge would act as a small weir and would not cause a significant change in the water level.

The following three pages show the calculations using the Chezy equations for the original river channel, the lake itself, and the dredged channels that could be used under the bridges.

 

water level

272

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

265

274

32

ft equiv. gage reading

rise (ft)

12.00

12.00

12.00

0.70

ft rise per river mile

run (ft)

90800

63500

63500

1.00

ft rise per reach mile(somewhat

height (ft)

26.0

7.0

-2.0

straight line down floodplain)

width (ft)

200

3800

12000

264.4

ft water surface-RM284.5

n (friction coef.)

0.03

0.2

0.2

276.4

ft water surface-RM301.7

velocity (ft/sec)

4.72

0.45

0.00

flowrate (cubic ft/sec)

24535

11981

0

total flow (cubic ft/sec)

36515

36515

The above calculations are for an average cross-section of the Pearl River in Jackson as it existed before the levees, bridges, or any other structures were built. For calculation purposes the cross-section is located at River Mile 294 which is roughly at the half way point of the upper lake. Different water levels and their resulting flowrates can be compared to the historical Jackson gage readings to make sure we are in the ball park with our friction factors and cross-sectional shape. The extrapolated water levels are based on reach distance rather than river miles.

Average

water level

274

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

265

274

34

ft equiv. gage reading

rise (ft)

12.00

12.00

12.00

0.70

ft rise per river mile

run (ft)

90800

63500

63500

1.00

ft rise per reach mile(somewhat

height (ft)

28.0

9.0

0.0

straight line down floodplane)

width (ft)

200

3800

12000

266.4

ft water surface-RM284.5

n (friction coef.)

0.03

0.2

0.2

278.4

ft water surface-RM301.7

velocity (ft/sec)

4.95

0.56

0.00

flowrate (cubic ft/sec)

27709

19315

0

total flow (cubic ft/sec)

47024

47024

The average water level is increased in two ft. increments and will be placed on a curve that shows the historical data

Average

water level

276

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

265

274

36

ft equiv. gage reading

rise (ft)

12.00

12.00

12.00

0.70

ft rise per river mile

run (ft)

90800

63500

63500

1.00

ft rise per reach mile(somewhat

height (ft)

30.0

11.0

2.0

straight line down floodplane)

width (ft)

200

3800

12000

268.4

ft water surface-RM284.5

n (friction coef.)

0.03

0.2

0.2

280.4

ft water surface-RM301.7

velocity (ft/sec)

5.17

0.68

0.14

flowrate (cubic ft/sec)

31025

28229

3401

total flow (cubic ft/sec)

59253

62655

It is also interesting to note that the extrapolated water levels at RM284.5 and RM301.7 are within a foot of the before

levee HEC-2 study that we did using many cross-sections. This is accurate enough for conceptual purposes to

come up with rough dimensions and water levels of a flood control lake.

Average

water level

278

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

265

274

38

ft equiv. gage reading

rise (ft)

12.00

12.00

12.00

0.70

ft rise per river mile

run (ft)

90800

63500

63500

1.00

ft rise per reach mile(somewhat

height (ft)

32.0

13.0

4.0

straight line down floodplain)

width (ft)

200

3800

12000

270.4

ft water surface-RM284.5

n (friction coef.)

0.03

0.2

0.2

282.4

ft water surface-RM301.7

velocity (ft/sec)

5.39

0.78

0.27

flowrate (cubic ft/sec)

34477

38664

13001

total flow (cubic ft/sec)

73141

86142

Average

water level

280

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

265

274

40

ft equiv. gage reading

rise (ft)

12.00

12.00

12.00

0.70

ft rise per river mile

run (ft)

90800

63500

63500

1.00

ft rise per reach mile(somewhat

height (ft)

34.0

15.0

6.0

straight line down floodplain)

width (ft)

200

3800

12000

272.4

ft water surface-RM284.5

n (friction coef.)

0.03

0.2

0.2

284.4

ft water surface-RM301.7

velocity (ft/sec)

5.60

0.89

0.39

flowrate (cubic ft/sec)

38063

50569

28288

total flow (cubic ft/sec)

88632

116920

Average

water level

280.6

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

265

274

40.6

ft equiv. gage reading

rise (ft)

12.00

12.00

12.00

0.70

ft rise per river mile

run (ft)

90800

63500

63500

1.00

ft rise per reach mile(somewhat

height (ft)

34.6

15.6

6.6

straight line down floodplain)

width (ft)

200

3800

12000

273.1

ft water surface-RM284.5

n (friction coef.)

0.03

0.2

0.2

285.1

ft water surface-RM301.7

velocity (ft/sec)

5.66

0.92

0.43

flowrate (cubic ft/sec)

39213

54597

34195

total flow (cubic ft/sec)

93811

128006

The flowrate in this situation is the same as that of the 1979(200year) flood but the water levels are that of a cross-section from the earlier part of this century.

Below is the same graph of historical peak flowrates vs. gage readings as shown earlier except that it has the above calculated information added on the graph.

fc_chart_pg20.gif (7195 bytes)

 

Average

water level

275.1

ft elev

@R.M.294

channel

river bottom

flat woods

av.bottom (elevation)

246

259

264

35.1

ft equiv. gage reading

rise (ft)

3.19

3.19

3.19

0.19

ft rise per river mile

run (ft)

90800

63500

63500

0.27

ft rise per reach mile(somewhat

height (ft)

29.1

16.1

11.1

straight line down floodplain)

width (ft)

200

2000

1200

273.1

ft water surface-RM284.5

n (friction coef.)

0.03

0.03

0.03

276.3

ft water surface-RM301.7

velocity (ft/sec)

3.19

2.59

1.96

flowrate (cubic ft/sec)

18540

83364

26103

total flow (cubic ft/sec)

101904

128007

Here is the 1979 flood again except the dredged lake is in place. You can see that there is only a three foot rise over a linear distance of 11 miles(16.5 river miles). This would lower the 200 year flood about 12 feet from present conditions at the reservoir.

Average

water level

275.1

ft elev

channel

av.bottom (elevation)

243

35.1

ft equiv. gage reading

rise (ft)

0.05

0.26

ft rise per mile

run (ft)

1000

height (ft)

32.1

width (ft)

1000

275.08

ft water surface-south

n (friction coef.)

0.03

275.12

ft water surface-north

velocity (ft/sec)

3.99

flowrate (cubic ft/sec)

128001

Here is an example of what could be done under the bridges. They could be dredged down to a level which would would not harm the bridge piles over a width of one thousand feet and have similar flow characteristics(water levels & gradients) as the lake itself. They would not silt back up because the water velocity of the lake would not be enough to carry sand.

 

map_pg22left.gif (149161 bytes)

map_pg22right.gif (148818 bytes)

 

Weirs

There are two weirs or low head dams on the lake. The southern most weir would hold a lake level of about 260 feet. The upper weir would hold the main body of the lake at a level of about 270 feet. The energy equation was used for the preliminary design of the weirs.

fc_chart_pg22.gif (16471 bytes)

WEIR OBSERVATIONS

     During major floods, such as the one that occurred in 1979, the flood control lakes will act as a river which is flowing on a grade. In order to understand what effect the submerged weirs will have when the flood control lakes are flowing on a grade, the pump house weir in the city of Jackson was studied and observed at various flow velocities and submergence heights.

     The example of actual flow over the pump house weir, shown in the charts below, is used in this report because the rate of flow per foot of weir (82.2 cubic feet per second) is almost identical to the rate of flow per foot of weir that will occur over the lower flood control lake weir during a 1979 flood (85.3 cubic feet per second).

     A person would not need to understand weir formulas to safely adjudge that an identical volume of water will pass over the lower lake weir with less elevation difference than will pass over the pump house weir. This is because the same rate of water passing over the pump house weir (which is 8.2 feet deep) has 12.6 feet of depth with which to pass over the lower lake weir.

     Velocity is, therefore, much less over the lower lake weir than at the observed pump house weir and, because velocity effects are exponential, calculations show that the upstream elevation increase, caused by the lower lake weir, will be approximately 0.26 feet, or, approximately one-half the effect observed at the pump house weir (0.57 feet).

WeirObservations

 

JACKSON, MISSISSIPPI
WATER INTAKE DAM
(LOCATED ON PEARL RIVER)

fc_chart_pg22btop.gif (4022 bytes)

 

LOWER LAKE WEIR

fc_chart_pg22bbottom.gif (4143 bytes)

 

 

MEMORANDUM


TO:         Matt Lamar (McGowan Working Partners) DATE: November 9, 1999

FROM: Gary Lake (Golder Associates Inc.)

RE:         UPPER AND LOWER WEIR CALCULATIONS FOR FLOOD CONTROL LAKE IN MISSISSIPPI


In your e-mail message to Mike Jacobs of Golder Associates Inc. (Lakewood, Colorado) on November 2, 1999, you requested that a hydraulics evaluation be made for two weir sites located on a flood control lake in Mississippi. Specifically, four situations were presented by you for Golder to calculate flood water levels above the two weir sites (designated as Lower Lake Weir and Upper Lake Weir) based on the hydraulics information and data you provided on Sheets 1 through 4 included with your e-mail message. Also, Golder understands that the calculated water surface elevations may be used in further HEC-2 computer model runs to be made by McGowan Working Partners. In addressing your request, two situations at each weir site were evaluated by Golder using the principles of submerged weir flow hydraulics for low dams.

 

The four flood situations you indicated are represented by water surfaces downstream of the weirs that are higher than the crest elevations for each situation and where the tailwater depths are so high that the characteristic "train" of surface waves at the weir site would be flattened out and disappear except for a dip in the water surface over the downstream side of the weir itself. Thus, the weirs are said to be submerged or drowned, and the water below the weirs is termed tailwater. The depth of submergence is the difference in elevation between a given tailwater surface and the crest of the weir. The discharge over a submerged weir is related to the head on the upstream side of the weir, the head at the downstream side, and the height of the weir crest above the channel bottom.

 

The following equation developed by Du Buat (discussed in Elements of Hydraulic Engineering, D.S. Ellis, 1947) was used to estimate flood water levels above the weir sites for the four weir flow situations, denoted as Cases 1 through 4 below. This submerged weir flow equation historically has primarily been used for establishing designs of regulating weirs on river systems and gives reliable results for evaluating existing river regulating weir systems under submerged flow conditions.

 

where:

d = submerged water depth, in feet;

H = upstream head depth on weir crest;

L = length of weir, in feet;

C = coefficient determined from tests on submerged weirs as used for river regulation and control, dimensionless; values of C for the following values of d/H are noted below; and

 

d/H
Value

C
Value

0.000

3.74

0.100

3.70

0.200

3.70

0.300

3.75

0.400

3.82

0.500

3.93

0.600

4.18

0.700

4.61

0.800

5.36

0.900

6.64

0.985*

9.19*

* upper limit of test data

Q = total discharge of 128,000 cfs.

Several iteration analyses were made to calculate a value of H for each case. A summary of the calculated upstream water levels for the weir sites (Cases 1 through 4, two cases for Upper Lake Weir site and two cases for Lower Lake Weir site) is presented below. The calculations are based solely on using the physical and hydraulics data you provided, and assuming the downstream water levels you cited represent the tailwater conditions, either as measured or calculated by others.

 

Case 1 (Lower Lake Weir)

Given:

weir crest elevation @ 260 ft.
weir length @ 1500 ft.
downstream water level elevation @ 273.30 ft.
channel bottom elevation @ 250 ft.

Calculated upstream water level elevation @   273.51

 

Case 2 (Lower Lake Weir)

Given:

weir crest elevation @ 260 ft.
weir length @ 2500 ft.
downstream water level elevation @ 273.30 ft.
channel bottom elevation @ 250 ft.

Calculated upstream water level elevation @   273.37

 

Case 3 (Upper Lake Weir)

Given:

weir crest elevation @ 269.5 ft.
weir length @ 3500 ft.
downstream water level elevation @ 274.50 ft.
channel bottom elevation @ 251.5 ft.

Calculated upstream water level elevation @   274.95

 

Case 4 (Upper Lake Weir)

Given:

weir crest elevation @ 266 ft.
weir length @ 3500 ft.
downstream water level elevation @ 274.50 ft.
channel bottom elevation @ 251.5 ft.

Calculated upstream water level elevation @   274.58

 

The calculated difference between upstream and downstream water depths for Case 1 (Lower Lake Weir site) is 0.21 foot and the calculated average approach flow velocity is 3.63 fps for the reported unit discharge of 85.3 cfs/ft width of flow. For Case 2 (Lower Lake Weir site), the reported unit discharge is 51.2 cfs/ft width of flow and the calculated average approach flow velocity is 2.19 fps. The calculated average approach flow velocities upstream of the Upper Lake Weir site for Cases 3 and 4 is 1.56 and 1.58 fps, respectively. For the purpose of modeling the four weir flow cases using the submerged weir flow equation, a reasonableness check was also made concerning the Pearl River low head dam and the reported water levels for January 10, 1997. For this low dam, the measured data indicated a 0.57-foot difference in water levels upstream and downstream of the dam for a reported unit discharge of 82.2 cfs/ft width of flow and average approach flow velocity of 4.29 fps. A calculated C value using the submerged weir flow equation is 8.09 and is considered very reasonable in accordance with the C values noted above.

 

If you should have any questions concerning these results of the hydraulic analyses presented herein, please contact me at (303) 980-0540 or email glake @golder.com. As we discussed yesterday, Golder shall invoice McGowan Working Partners in the amount of $1,300.00 for the engineering services rendered. If Golder Associates can provide further engineering assistance to McGowan Working Partners, please call Mike Jacobs or myself at the phone number indicated above.

 

Thank you,

 

Gary Lake, P.E.

 

E1 = E3 – hL(1-3)

For simplicity set E1 = E2 = E3

and E = z + y + V2/2g

Where:

V = Q/Area = q/y

q = flow rate Q ¸ Width of weir channel

g = Gravity = 32.2 ft/sec2

y = Fluid depth

y2 = Critical depth of weir; yc = (q2/gn)1/3

z2 = Height of weir

If the weirs are designed properly, the flow during a 200 year flood could approach the weir at subcritical flow, pass over the weir at critical flow and return to subcritical flow with little or no rise above the normal hydraulic gradient of the lake itself. It was calculated that for an upper weir height of 269.5 feet, it would take a width of at least 3500 feet to allow 128,000 cubic feet per second to pass through without causing a significant change in the upstream water surface elevation.

 

3500 FT WEIR TOP AT 269.5

*W.S.elev

upstream

Q

q

y(crit)

(v^2)/2gn

E

over weir

W.S.elev

128000

37

3.5

1.7

5.2

273.0

274.6

100000

29

2.9

1.5

4.4

272.4

273.8

90000

26

2.7

1.4

4.1

272.2

273.6

80000

23

2.5

1.3

3.8

272.0

273.3

70000

20

2.3

1.2

3.5

271.8

272.9

60000

17

2.1

1.0

3.1

271.6

272.6

50000

14

1.9

0.9

2.8

271.4

272.3

40000

11

1.6

0.8

2.4

271.1

271.9

30000

9

1.3

0.7

2.0

270.8

271.5

20000

6

1.0

0.5

1.5

270.5

271.0

10000

3

0.6

0.3

0.9

270.1

270.4

5000

1

0.4

0.2

0.6

269.9

270.1

1000

0

0.1

0.1

0.2

269.6

269.7

*The flow over the weir has a reduced water surface elevation due to the high flow rate. When the downstream flow returns to a subcritical flowrate, the water surface elevation returns to the normal level which can be as high as the upstream level depending upon the downstream head.

 

 

4000 FT WEIR TOP AT 269.5

*W.S.elev

upstream

Q

q

y(crit)

(v^2)/2gn

E

over weir

W.S.elev

128000

32

3.2

1.6

4.8

272.7

274.2

100000

25

2.7

1.3

4.0

272.2

273.5

90000

23

2.5

1.3

3.8

272.0

273.2

80000

20

2.3

1.2

3.5

271.8

272.9

70000

18

2.1

1.1

3.2

271.6

272.6

60000

15

1.9

1.0

2.9

271.4

272.3

50000

13

1.7

0.8

2.5

271.2

272.0

40000

10

1.5

0.7

2.2

271.0

271.7

30000

8

1.2

0.6

1.8

270.7

271.3

20000

5

0.9

0.5

1.4

270.4

270.9

10000

3

0.6

0.3

0.9

270.1

270.4

5000

1

0.4

0.2

0.5

269.9

270.0

1000

0

0.1

0.1

0.2

269.6

269.7

*The flow over the weir has a reduced water surface elevation due to the high flow rate. When the downstream flow returns to a subcritical flowrate, the water surface elevation returns to the normal level which can be as high as the upstream level depending upon the downstream head.

 

With the southern most weir being at a height of 260, a width of 1000 feet would be adequate. A width of 1500 feet however would hold the lower lake at a more stable level.

 

 

1000 FT WEIR TOP AT 260

*W.S.elev

upstream

Q

q

y(crit)

(v^2)/2gn

E

over weir

W.S.elev

128000

128

8.0

4.0

12.0

268.0

271.4

100000

100

6.8

3.4

10.2

266.8

269.8

90000

90

6.3

3.2

9.5

266.3

269.1

80000

80

5.8

2.9

8.8

265.8

268.5

70000

70

5.3

2.7

8.0

265.3

267.8

60000

60

4.8

2.4

7.2

264.8

267.0

50000

50

4.3

2.1

6.4

264.3

266.3

40000

40

3.7

1.8

5.5

263.7

265.4

30000

30

3.0

1.5

4.6

263.0

264.5

20000

20

2.3

1.2

3.5

262.3

263.4

10000

10

1.5

0.7

2.2

261.5

262.2

5000

5

0.9

0.5

1.4

260.9

261.4

1000

1

0.3

0.2

0.5

260.3

260.5

*The flow over the weir has a reduced water surface elevation due to the high flow rate. When the downstream flow returns to a subcritical flowrate, the water surface elevation returns to the normal level which can be as high as the upstream level depending upon the downstream head.

 

 

1500 FT WEIR TOP AT 260

*W.S.elev

upstream

Q

q

y(crit)

(v^2)/2gn

E

over weir

W.S.elev

128000

85

6.1

3.0

9.1

266.1

268.8

100000

67

5.2

2.6

7.8

265.2

267.5

90000

60

4.8

2.4

7.2

264.8

267.0

80000

53

4.5

2.2

6.7

264.5

266.5

70000

47

4.1

2.0

6.1

264.1

266.0

60000

40

3.7

1.8

5.5

263.7

265.4

50000

33

3.3

1.6

4.9

263.3

264.8

40000

27

2.8

1.4

4.2

262.8

264.2

30000

20

2.3

1.2

3.5

262.3

263.4

20000

13

1.8

0.9

2.7

261.8

262.6

10000

7

1.1

0.6

1.7

261.1

261.7

5000

3

0.7

0.4

1.1

260.7

261.1

1000

1

0.2

0.1

0.4

260.2

260.4

*The flow over the weir has a reduced water surface elevation due to the high flow rate. When the downstream flow returns to a subcritical flowrate, the water surface elevation returns to the normal level which can be as high as the upstream level depending upon the downstream head.

 

Capacity

The effect of the lost capacity due to this lake is explained in detail on page 103 of the lake plan.

 

HEC-2 Computer Model

In order for any concept such as this lake to be considered it must be applied to an accepted computer model. This plan was applied to the Corps of Engineers "HEC-2" stream channel analysis computer program. The results confirmed that the long hand calculations were in the ball park. A modification must be made on the upper lake’s weir to get the HEC-2 to have proper water surface elevations. The top of the weir had to be entered as having an elevation of 267 feet. The true dimensions may be confirmed with the energy equation or long hand calculations. The hands on HEC-2 guide states on page 1-2 under limitations that "Profile computations are not allowed To Pass through critical depth. Sub critical and super critical analyses must be performed separately". The results of the HEC-2 analysis for a flow rate of 128,000 cubic feet per second follow

 

DTLAKE.OUT
FLOODWAY DATA,
PROFILE NO.  2
200 YEAR FLOOD 128000 Line 3346 Col 1

-------------------- FLOODWAY --------------------

---------- WATER SURFACE ELEVATION ----------

STATION WIDTH SECTION
AREA
MEAN
VELOCITY
WITH
FLOODWAY
WITHOUT
FLOODWAY
DIFFERENCE
253.950 6976. 69109. 1.9 251.8 251.8 .0
254.820 7050. 73017. 1.8 253.0 252.9 .1
54.839 9010. 43290. 3.0 252.6 252.5 .1
54.847 9017. 43773. 2.9 252.7 252.5 .2
54.865 6304. 69664. 1.8 253.6 253.7 -.1
257.050 8319. 91902. 1.4 255.4 255.2 .2
59.194 9193. 103056. 1.2 257.0 256.8 .2
59.213 9236. 87574. 1.5 257.2 257.0 .2
59.221 9226. 87723. 1.5 257.3 257.1 .2
259.270 6754. 84234. 1.5 257.3 257.1 .2
262.270 6610. 93167. 1.4 259.6 259.0 .6
264.450 6678. 94316. 1.4 261.3 260.6 .7
266.220 11360. 146590. .9 262.8 262.0 .8
268.870 9648. 118954. 1.1 264.2 263.3 .9
270.440 1581. 26125. 4.9 265.3 264.4 .9
270.530 1581. 26852. 4.8 265.8 264.9 .9
70.584 1581. 26656. 4.8 265.8 264.9 .9
70.591 1581. 26673. 4.8 265.8 264.9 .9
70.610 6171. 85682. 1.5 267.4 266.7 .7
273.310 7499. 96611. 1.3 268.3 267.6 .7
277.110 10293. 145400. .9 270.1 269.2 .9
278.980 10340. 104832. 1.2 271.0 270.1 .9
282.080 9479. 113419. 1.1 272.9 272.1 .8
282.890 9922. 99896. 1.3 273.2 272.5 .7
283.610 10185. 175277. .7 273.8 273.1 .7
284.420 9772. 148876. .9 274.0 273.3 .7
284.500 7350. 124586. 1.0 274.0 273.3 .7
285.070 1500. 51067. 2.5 274.0 273.3 .7
85.087 1500. 22266. 5.7 273.9 273.1 .8
85.088 1500. 22267. 5.7 273.9 273.1 .8
285.110 1500. 51589. 2.5 274.4 273.7 .7
285.350 2862. 64366. 2.0 274.5 273.8 .7
286.250 959. 30020. 4.3 274.5 273.8 .7
286.630 1038. 31836. 4.0 274.6 273.9 .7
286.970 998. 30348. 4.2 274.7 274.0 .7
287.370 1132. 32280. 4.0 274.9 274.2 .7
287.540 3500. 116246. 1.1 275.2 274.5 .7
87.559 3500. 31844. 4.0 275.1 274.4 .7
87.560 3500. 31847. 4.0 275.1 274.4 .7
87.579 3500. 116909. 1.1 275.4 274.8 .6
DTLAKE.OUT Line 3393 Col 1
87.579 3500. 116909. 1.1 275.4 274.8 .6
287.820 2871. 52079. 2.5 275.3 274.7 .6
288.230 3215. 29266. 4.4 275.2 274.6 .6
288.990 5387. 75360. 1.7 275.7 275.0 .7
289.460 5390. 75664. 1.7 275.7 275.1 .6
290.080 5393. 75982. 1.7 275.8 275.2 .6
290.400 5395. 76142. 1.7 275.8 275.2 .6
290.500 4870. 51805. 2.5 275.8 275.2 .6
290.530 4869. 51786. 2.5 275.8 275.2 .6
290.600 5398. 76414. 1.7 275.9 275.3 .6
291.810 5590. 76406. 1.7 276.0 275.4 .6
292.340 3110. 49750. 2.6 276.0 275.4 .6
92.549 1987. 26658. 4.8 275.9 275.3 .6
293.790 3389. 65546. 2.0 276.7 276.0 .7
295.190 3038. 54086. 2.4 276.9 276.2 .7
295.490 3037. 54255. 2.4 276.9 276.2 .7
296.690 3419. 59644. 2.1 277.1 276.4 .7
298.310 4153. 72636. 1.8 277.3 276.6 .7
299.800 2540. 46080. 2.8 277.4 276.7 .7
300.280 3431. 54138. 2.4 277.7 276.9 .8
301.290 1898. 33683. 3.8 278.0 277.3 .7

 

Conclusion

As stated in the lake plan, these figures are by no means set in stone. This is a concept. If it turns out that these lake dimensions are not adequate, or more than adequate, the proper depths and widths can be determined.

The following pages contain a hydraulic evaluation of this lake pan by Golder Associates. The firm was hired by John McGowan and Mart Lamar to verify the work that is presented in this plan.

 

MAXIMUM BENEFITS THAT WILL RESULT FROM THE
FLOOD CONTROL LAKES ALONE WITH NO ADDITIONAL BENEFIT
FROM RESERVOIR REGULATION
Flood benefits at 1979 Flow Rate
350 Year Probability

Position River
Mile
Location

1979
Actual

Flood
Lake
Elevation
McGowan
Evaluation

Flood
Lake
Flood
Benefit
McGowan
Flood
Lake
Elevation
Golder
Evaluation
  1. Richland Flood Plain 284.5 272.9 273.3 capacity effect + 0.4 feet (272.9) 128,000 cfs actual
  2. Lynch Creek 286.4 276.6 273.8 -  2.8 (273.2) 0.10 ft over lower weir
  3. Town Creek 287.4 277.7 274.2 -  3.5 (273.5)
  4. Island South End 288.5 281.0 275.0 -  6.0 (274.9)0.89 ft over upper weir
  5. Island North End 292.3 283.7 275.2 -  8.5 (275.3)
  6. The Quarter 292.5 283.7 275.2 -  8.5 (275.3)
  7. Twin Lake Subdivision 293.0 284.0 275.7 -  9.2 (275.8)
  8. Canterbury Court SBV 294.0 285.8 276.0 -  9.8 (275.9)
  9. Hanging Moss Creek 295.8 286.4 276.1 -10.3 (276.1)
10. McLeod SBV 296.5 286.8 276.3 -10.5 (276.2)
11. Canton Club SBV 298.0 287.1 276.5 -10.6 (276.4)
12. Dam 301.3

288.4

277.0

-11.4 (277.4)

     At the present time it is very difficult to utilize the flood prevention capabilities of the Barnett Reservoir. Creation of flood control lakes below the reservoir will enable the reservoir to prerelease in advance of major storms without flooding homes and businesses in Jackson. This ability will enable the reservoir to reduce flooding downstream in Richland and Byram.

MAXIMUM BENEFITS THAT CAN BE DERIVED BY SUBTRACTING AN
APPROXIMATE ADDITIONAL 1.23 FEET THAT WILL RESULT FROM
IMPROVED REGULATION OF THE RESERVOIR.

Benefits derived from reservoir regulation will be discounted according to the consistency with which reservoir inflow can be predicted from rainfall as it is measured on the ground. This discount value will be applied to the chart below when a computer model for inflow projection has been completed.

Position 1979
Actual
Flood
Level

Flood
Lake
Level
With improved
Discharge

Cumulative
Flood
Benefits
  1. Richland Flood Plain 272.9 272.0 -  0.9 feet
  2. Lynch Creek 276.6 272.6 -  4.0
  3. Town Creek 277.7 272.9 -  4.8
  4. Island South End 281.0 273.9 -  7.1
  5. Island North End 283.7 274.2 -  9.5
  6. The Quarter 283.7 274.2 -  9.5
  7. Twin Lake Subdivision 284.0 274.7 -10.2
  8. Canterbury Court SBV 285.8 275.0 -10.8
  9. Hanging Moss Creek 286.4 275.1 -11.3
10. McLeod SBV 286.8 275.3 -11.5
11. Canton Club SBV 287.1 275.5 -11.6
12. Dam 288.4 276.0 -12.4
Home | Foreword | Jackson Gateway | Solution | Flood Control Benefit | Community Enhancement | Development Opportunities | Reservoir Inflow Projections | Retention vs. Conveyance | Summary | Voice Your Opinion | Photo Gallery | Site Map