ANSWER TO U.S.
CORPS OF ENGINEERS CONCERN NUMBER
5
The extensive
channel modifications could result in channel instability
which could also extend up tributaries of the Pearl
River.
The lake level is
supposed to provide a much slower flow rate during all of the time
that the river is not on flood. It will prevent the constant
movement and redistribution of sand that occurs continuously in a
steeply flowing river channel. The main flow coming into the lake
will be relatively clean water from the reservoir. Silting will
occur in the tributary estuaries in the same manner that silting is
occurring now in the tributaries along the lower reservoir. This
silt can be recognized from original lake bottom. A measurement of
the amount of silting coming from a given watershed with heavy
residential development can be determined in the reservoir. From the
30 year history of silting on reservoir tributaries it can be
determined how much extra dredging will be needed in the estuaries
to accommodate this silt for a long time. An amount could be removed
that would be calculated to provide a 100 year maintenance free flow
channel in the flood control lakes. Most of the sand that exists
between the levees and bridges south of downtown Jackson would be
removed leaving no sand to be redistributed in the lowest most lake.
Preliminary estimates are that about four million yards of
additional dredgings would be required.
SEDIMENT ENTERING THE
LAKE
Creeks below
the Barnett Reservoir dam will carry sediment. The flood control
lake as a 140 square mile watershed form these sources. The 1998
USGS quadrangles show approximately 70% of the area developed into
mature residential subdivision and business areas. It is estimated
that 30% of the watershed remains subject to development. Very
little farming occurs in this area. Observation of creeks during
flash floods reveals that the metropolitan creeks do not carry high
concentrationa of sediment.
One of the
most extensive areas for recent development is in the area along
Mill Creek which flows into the reservoir. Subdivisions extend all
the way to its headwaters near Brandon. Over 20% of this upland area
not in subdivision has, until recently, been formed in wheat and
soybeans. Much of this farming has recently been discontinued.
Erosion from this area during the past 15 years has deposited
approximately 100,000 years of sediment in the reservoir. This
amount of sediment has been dredged by the reservoir wngineers to
keep boat docks open in the creek estuary. Complete development of
this watershed could result in as much as 200,000 additional yards
of sediment settling in the reservoir over the next 30 to 50 years.
Other studies conducted on residential lakes reveal that similar
amounts of sediments collect in them during development and that
very lettle sedimentation accurs after the development has
ended.
The Mill
Creek watershed is appriximately one-tenth the cumulative sediment
bearing watershed of the flood control lake. If all of the lakes'
watershed were subject to development and farming, such as the Mill
Creek watershed, approximately three to four million years of
sediment could be estimated to enter the lake over the next 100
years. However, since only 30 percent of the area remains to be
developed and little re-development is expected in the mature areas,
as little as one million yards could enter the lake in 100 years.
Additionally, Department of Environmental Control regulations now
reqire that sediment be contained on construction sights. This
should reduce the amount of sediment that future construction will
contribute to the flood control lake.
This plan
calls for overdredging the creek estuaries to accommodate heavy
sediment from the tributary watershed such that it will not enter
the flood control lake. Two to four million yards should accomplish
this with a two to four safety factor for 100 years. Very fine sand
and colloidal material will enter the lake.
SEDIMENT TRANSPORTATION IN
THE LAKE
The flood control lake will occupy
the lower meander belt (riverbottom land) of the two mile wide Pearl
River flood plain. This belt of land averages 3000' wide and is at a
level approximately nine feet lower than the upper level terraces
(flatwoods) of the flood plain. Material in the lower level meander
belt consists of sandbars (fine to coarse grain clean to silty sand)
that rests upon a hard blue clay (see cross-section below). Sand
thickness ranges from 25 fet at the crest of sandbars to five feet
in the lowest troughs. This sand averages 15 feet thick.

Dredging
will remove approximately 40 jpercent of this sand. The rest will be
planed off and remain on the bottom of the lake. The sandbar
material dredged from the lake will be fine to coarse grain quartz
sand. This material will remain also on the lake bottom. We have
made observations of sand movement in high enerby flow over sandbars
in a effort ot develop judgement as to how this sand will act during
times when major floods pass though the lake. See map of the Pearl
River channel below.

POSITION
1
Stream flow
2-1/2 inches deep over medium grain (.25 to .50 mm) sand was
measured at a velocity of 0.80 ft/sec at the surface. No movement of
sand was occuring. The surface of the sand was smooth and had an
orange color. Some areas had a greenish, pulp like coating
approximately 1/16 inch thick. Breaking the ripples revealed that
the sand was gray in color and that the orange coating was on the
surface only. The underlying sand would not move when the surface is
broken. A 4 oz cup of clean gray sand was deposited on the sand
bottom surface and observed. Stream flow flattened the pile of sand
out over an area about 6 inches wide and 10 inches long in the
downstream direction. No further movement occurred. Observed for 2
hours. Sand grains placed on a metal measuring tape 1/4 inch above
bottom were observed. They would not roll on the tape, indicating
that velocity in the bottom 1/4 inch was not sufficient to move the
sand grains.
POSITION
2
Stream flow
2-1/2 inches deep was measured at a velocity of 1.25 ft/sec at the
surface. No movement of sand was occuring. Sand size was
measured to be .25 to .50 mm. The surface of the sand bottom had
"flagstone" ripples and an orange stain. Sand movement is by
sporatic movement f individual grains. Two 4 oz cups of clean gray
sand were deposited on the sand bottom surface. These piles were
flattened by the stream flow into dune shaped flagstone ripples
covering an area approximately 6 inches wide and 10 inches long.
Sand grains continued to move by sporatic dislodging and lodging of
individual sand grains.
One sand
dune was scattered to break up its shape. In its flattened
condition, sand movement occurred at a more rapid pace (still
individual lodging and dislodging of individual sand grains). After
2 hours, sand had trailed our in a downstream direction 3 feet,
moving over the orange stained encrusted sand surface in a laminate
1/16' thick or less.
The sand
dune that had not been flattened retained its shape and moved
approximately 4 inches downstream in 30 minutes. It then began to
become incrusted with a greenish orange material and after 1 hour
stopped moving.
Sand was
scooped up along with a layer of this greenish pulp coating and
deposited in a 4 oz. pile. This pile flattened and retained a
shallow mound shape. It developed a partial coating of the greenish
mineral matter and stopped moving after 5 minutes. After 1 hour this
mound developed a slight ripple mound shape.
This same
area was observed 24 hours later. The depth had decreased to 1-1/4
inches. Velocity of flow had only slightly decreased to 1.10 ft/sec
at the surface. Individual sand grains were moving on the sand
bottom surface over the general area in trace amounts. The greenish
pulp surface was observed to be eroding in small areas with
increased sand movement in the eroded areas. Clean sand in 4 oz.
piled would flatten and move by lodging and dislodging of sand
grains. These piles string out in the downstream direction 3 feet in
30 minutes. Flow appeared to be more erosive than the previous day
with the only known change being that the depth was reduced form
2-1/2 inches to 1-1/4 inches . After observing the shallow bar where
velocities remained close to 1 foot per second for 7 days, the bar
did not change shape and moved downstream about 1 inch.
POSITION
3
This
position on the outside of the channel bend was 32 inches deep.
Stream flow velocity was measured at 1.90 ft/sec. Bottom could not
be seen at this depth. Material on the bottom was measured to ve
medium (.2 to .6 mm) grain quartz sand. A 4 oz. cup was buried flush
with the bottom and observed for full. After 1 hour no sand settled
out in the cup. Flow around the leading edge of the cup and sides,
dished out sand to a depth of 1/4 inch. It was determined that at
this depth and velocity, stream flow could not suspend .2 to .6 mm
sand grains. By holding a 5 foot cane rod in one hand perpendicular
to the stream flow and gauging the pressure created by the flow it
could be determined that much less occured when the cane rod was
held on the bottom surface, and pressure increased dramatically as
the rod was lifted to a level 10 inches above the bottom surface. By
suspending a 12 oz. plastic bottle filled with water on a fishing
cork, flow velocity was gauged a various depths. It could be seen
that flow velocity decreased to 1.5 feet per second in the bottom
foot of depth. Repeats of this test demonstrated a wide range of
results and the test was not considered to be very accurate. The
results, however, did show consistently lower velocities near
bottom. On the 7th day of testing, a 3/4 inch PVC tube was used to
gauge stream velocities at various depth by gauging flow pressure in
a clear static tube. Depth had increased to to 38 inches. Velocity
at the surface was 2.1 ft/sec. Velocities decreased slightly with
depth and dramatically in the bottom 6 inches. Velocity in the
bottom 1 inch was approximately 1 ft/sec. The sand bottom could not
be seen but felt slightly firm on top and it was determined that
sand grains were not suspended in the flow.
A history of
reservoir discharge was compiled to determine what flow rates could
be expected in the lake over the next 100 years (see tables and
graphs attached). A 200 year event was included in this 34 year
record and its effect was tripled in the 100 year estimation. This
tended to distort the graph at higher magnitude floods. From the
resulting table, it is estimated that flow rates in the lake will
exceed 1.25 ft/sec 47 days during the next 100 years. At this rate,
direct observation shows that the medium grain sand base in the lake
will not, as a practical matter, appreciable move. If the dand could
be kept perfecly clean it would develop a resistance shape
(flagstone ripples) and move as a thin laminate approximately up to
75 feet per day, 3500 feet in 100 years.
DEPOSITION OF COLLOIDAL
MUD
Colloidal material will
enter the lake from the strem estuaries and dehydrate into the
medium grain sand bottom of the lake. By observing the build-up of
sediment in residential lakes, beaver ponds and the reservoir it can
be estimated that a thick muddy bottom will develop in the lake over
the next 100 years. Colloidal mud with predominant particle size of
.005 to .015 mm settles out in beaver ponds which, when constructed
across creeks, experience frequent high velocity flow. Between
periods of high velocity flow, thse ponds do not dry up, slight flow
continues and colloidal particles are, nevertheless, able to
combine, attract and attach themselves to the bottom. It is expected
the this will also happen in the flood control lake during periods
when very little movement occurs. (See table showing mean lake
velocities.)
EFFECT OF MAJOR FLOODS ON A
MUD BOTTOM
In an effort
to develop judgement about how this mud bottom will react to flow
during major floods in the lake, we returned to the previous test
site. a one quarter inch thick layer of this material was placed on
spread metal sheets and placed in the Pearl River stream flow at
positions 2 and 3 on the sandbar to observe how it holds up and
resists erosion. Mud, about 1/4 inch thick, was laso spread upon the
sand bottom surface.
POSITION
2
After 4 days
no change was in the condition of the mud on the sand surface or on
the spread metal grid. At this time, the depth had increased from
2-1/2 inches and a velocity of 1.25 ft/sec and the velocity to 1.67
ft/sec.
POSITION
3
This area,
32 inches deep, was flowing at a velocity of 1.90 ft/sec at 1 foot
of depth. A spread metal grid with 0.005 to 0.015 mm mud spread upon
it was placed at the bottom surface. The mud was oserved for 4 days
and remained intact. At the end of the test, depth had increased to
38 inches and velocity to 2.1 ft/sec. This is approximately the same
velocity as will occure in the lake during a 100 year flood. The
time period (4 days) is also the same as the period that a 100 year
flood can be expected to flow at these rates. We used 3/4" PVC
tubing to gauge stream pressure at varying depth and estimated flow
velocity in the inch next to bottom to be approximately 1
ft/sec.
TRANSPORTATION OF SEDIMENT
THROUGH BRIDGES
At the
present time, major floods make effective use of the channel span of
the bridges only. These spans average approximately 350 feet width.
The other 2/3rds of the bridge opening is blocked by sandbars and
willow growth. This subjects the channel span to extreme flow which
erodes down to and into the blue clay. By opening up and deepening
the entire bridge section, average flow rates through the bridge
will be greatly reduced. In many cases, the removal of these
sandbars would free little more piling than exists at present on the
most exposed piling in the low elevation back swamp areas of the
bridge sections. Improved flow through the intire bridge section
must be studied by someone with experience in hydraulic analysis of
bridges to determine what, if any, provisions need to be made to
adapt the bridges to these new conditions.
CONCLUSION
Direct observation of high energy flow over flat sandbars
in the river indicates that the clean medium grain sand bottom forms
a resistance shape (flagstone ripples) and a packed surface which
resists erosion. Erosion begins to occure when flow velocity
approaches 1 ft/sec in the depth interval that is 1 inch above the
sand bottom. One ft/sec flow was observed in the 1 inch interval
above the sand bottom when 3 feet of water was flowing at 2.1 ft/sec
at the surface. (The mean velocity was calculated to be 1.8 ft/sec).
Assuming that similar velocities will occure in the lake (15 feet
deep) these rates may be expected to occur 26 days during the next
100 years. Nevertheless, it appears that the lake will experience
deposition of colloidal mud during close to 20,000 days over the
next 100 years. Since the lake will develop a mud bottom and, since
no flow is projected to occur in 100 years that will erode this type
of bottom, the lake should be maintenance free for 100
years,
|
|
|
|
|
|
Cross |
|
Days above |
Days below |
|
Reservoir |
Actual |
Days |
Cross |
|
Sectional |
Velocity |
Discharge |
Discharge |
|
Discharge |
Days |
Based on |
Sectional |
Mean Lake |
Under |
Under |
Rate per |
Rate per |
|
(CFS) |
Measured |
100
years |
Area of Lake |
Velocity |
Bridges |
Bridges |
100
Years |
100
Years |
|
Corrected |
250 |
4383 |
12,865 |
34,500 |
0.007 |
21,600 |
0.012 |
36,500 |
12,865 |
|
Corrected |
375 |
141 |
414 |
34,600 |
0.011 |
21,600 |
0.017 |
23,635 |
13,279 |
|
Corrected |
500 |
816 |
2,395 |
34,600 |
0.014 |
21,600 |
0.023 |
23,221 |
15,674 |
|
Corrected |
700 |
67 |
197 |
34,600 |
0.020 |
21,600 |
0.032 |
20,826 |
15,871 |
|
Corrected |
1500 |
1407 |
4,130 |
34,700 |
0.043 |
21,700 |
0.069 |
20,629 |
20,001 |
|
Corrected |
2500 |
914 |
2,683 |
34,900 |
0.072 |
21,700 |
0.115 |
16,499 |
22,684 |
|
As
Read |
4000 |
769 |
2,257 |
35,100 |
0.114 |
21,800 |
0.183 |
13,816 |
24,941 |
|
"
" |
5000 |
577 |
1,694 |
35,200 |
0.142 |
21,800 |
0.229 |
11,559 |
26,635 |
|
"
" |
6000 |
416 |
1,221 |
35,300 |
0.170 |
21,900 |
0.274 |
9,865 |
27,856 |
|
"
" |
7000 |
347 |
1,019 |
35,500 |
0.197 |
21,900 |
0.320 |
8,644 |
28,874 |
|
"
" |
8000 |
329 |
966 |
35,600 |
0.225 |
21,900 |
0.365 |
7,626 |
29,840 |
|
"
" |
9000 |
251 |
737 |
35,800 |
0.251 |
22,000 |
0.409 |
6,660 |
30,577 |
|
"
" |
10000 |
196 |
575 |
35,900 |
0.279 |
22,000 |
0.455 |
5,923 |
31,152 |
|
"
" |
11000 |
188 |
552 |
36,000 |
0.306 |
22,100 |
0.498 |
5,348 |
31,704 |
|
"
" |
12000 |
160 |
470 |
36,200 |
0.331 |
22,100 |
0.543 |
4,796 |
32,173 |
|
"
" |
13000 |
116 |
340 |
36,300 |
0.358 |
22,200 |
0.586 |
4,327 |
32,514 |
|
"
" |
14000 |
140 |
411 |
36,500 |
0.384 |
22,200 |
0.631 |
3,986 |
32,925 |
|
"
" |
15000 |
107 |
314 |
36,600 |
0.410 |
22,300 |
0.673 |
3,575 |
33,239 |
|
"
" |
16000 |
105 |
308 |
36,800 |
0.435 |
22,300 |
0.717 |
3,261 |
33,547 |
|
"
" |
17000 |
70 |
205 |
36,900 |
0.461 |
22,300 |
0.762 |
2,953 |
33,753 |
|
"
" |
18000 |
65 |
191 |
37,000 |
0.486 |
22,400 |
0.804 |
2,747 |
33,943 |
|
"
" |
19000 |
68 |
200 |
37,200 |
0.511 |
22,400 |
0.848 |
2,557 |
34,143 |
|
"
" |
20000 |
64 |
188 |
37,300 |
0.536 |
22,500 |
0.889 |
2,357 |
34,331 |
|
"
" |
21000 |
69 |
203 |
37,500 |
0.560 |
22,500 |
0.933 |
2,169 |
34,533 |
|
"
" |
22000 |
62 |
182 |
37,600 |
0.585 |
22,600 |
0.973 |
1,967 |
34,715 |
|
"
" |
23000 |
63 |
185 |
37,700 |
0.610 |
22,600 |
1.018 |
1,785 |
34,900 |
|
"
" |
24000 |
59 |
173 |
37,900 |
0.633 |
22,600 |
1.062 |
1,600 |
35,073 |
|
"
" |
25000 |
51 |
150 |
38,000 |
0.658 |
22,700 |
1.101 |
1,427 |
35,223 |
|
"
" |
26000 |
29 |
85 |
38,200 |
0.681 |
22,700 |
1.145 |
1,277 |
35,308 |
|
"
" |
27000 |
59 |
173 |
38,300 |
0.705 |
22,800 |
1.184 |
1,192 |
35,481 |
|
"
" |
28000 |
13 |
38 |
38,400 |
0.729 |
22,800 |
1.228 |
1,019 |
35,520 |
|
"
" |
29000 |
39 |
114 |
38,600 |
0.751 |
22,900 |
1.266 |
980 |
35,634 |
|
"
" |
30000 |
28 |
82 |
38,700 |
0.775 |
22,900 |
1.310 |
866 |
35,716 |
|
"
" |
31000 |
18 |
53 |
38,900 |
0.797 |
23,000 |
1.348 |
784 |
35,769 |
|
"
" |
32000 |
19 |
56 |
39,000 |
0.821 |
23,000 |
1.391 |
731 |
35,825 |
|
"
" |
33000 |
24 |
70 |
39,100 |
0.844 |
23,000 |
1.435 |
675 |
35,895 |
|
"
" |
34000 |
22 |
65 |
39,300 |
0.865 |
23,100 |
1.472 |
605 |
35,960 |
|
"
" |
35000 |
32 |
94 |
39,400 |
0.888 |
23,100 |
1.515 |
540 |
36,054 |
|
"
" |
36000 |
12 |
35 |
39,600 |
0.909 |
23,200 |
1.552 |
446 |
36,089 |
|
"
" |
37000 |
14 |
41 |
39,700 |
0.932 |
23,200 |
1.595 |
411 |
36,130 |
|
"
" |
38000 |
12 |
35 |
39,800 |
0.955 |
23,300 |
1.631 |
370 |
36,165 |
|
"
" |
39000 |
16 |
47 |
40,000 |
0.975 |
23,300 |
1.674 |
335 |
36,212 |
|
"
" |
40000 |
14 |
41 |
40,100 |
0.998 |
23,300 |
1.717 |
288 |
36,253 |
|
"
" |
41000 |
8 |
23 |
40,300 |
1.017 |
23,400 |
1.752 |
247 |
36,277 |
|
"
" |
42000 |
4 |
12 |
40,400 |
1.040 |
23,400 |
1.795 |
223 |
36,289 |
|
"
" |
43000 |
8 |
23 |
40,600 |
1.059 |
23,500 |
1.830 |
211 |
36,312 |
|
"
" |
44000 |
4 |
12 |
40,700 |
1.081 |
23,500 |
1.872 |
188 |
36,324 |
|
"
" |
45000 |
13 |
38 |
40,800 |
1.103 |
23,600 |
1.907 |
176 |
36,362 |
|
"
" |
46000 |
11 |
32 |
41,000 |
1.122 |
23,600 |
1.949 |
138 |
36,394 |
|
"
" |
47000 |
10 |
29 |
41,100 |
1.144 |
23,700 |
1.983 |
106 |
36,424 |
|
"
" |
48000 |
4 |
12 |
41,300 |
1.162 |
23,700 |
2.025 |
76 |
36,435 |
|
"
" |
50000 |
6 |
18 |
41,500 |
1.205 |
23,800 |
2.101 |
65 |
36,453 |
|
"
" |
60000 |
4 |
12 |
42,900 |
1.399 |
24,200 |
2.479 |
47 |
36,465 |
|
"
" |
70000 |
3 |
9 |
44,400 |
1.577 |
24,700 |
2.834 |
35 |
36,474 |
|
"
" |
80000 |
4 |
12 |
45,800 |
1.747 |
25,100 |
3.187 |
26 |
36,485 |
|
"
" |
100000 |
1 |
3 |
48,600 |
2.058 |
26,000 |
3.846 |
15 |
36,488 |
|
"
" |
110000 |
1 |
3 |
50,000 |
2.200 |
26,400 |
4.167 |
12 |
36,491 |
|
"
" |
120000 |
1 |
3 |
51,400 |
2.335 |
26,800 |
4.478 |
9 |
36,494 |
|
"
" |
130000 |
2 |
6 |
52,800 |
2.462 |
27,300 |
4.762 |
6 |
36,500 |
|
|
|
|
|
|
|
|
|
|
|
|
12,435 |
36500 |
|
|
|
|
|
|
|
|
|
|
|
|
Days above
|
Days below
|
|
Reservoir |
Actual |
Days |
Cross |
|
Discharge |
Discharge
|
|
Discharge |
Days |
Based on |
Sectional |
Mean Lake |
Rate per |
Rate per
|
|
(CFS) |
Measured |
100 years |
Area of Lake
|
Velocity |
100 Years |
100 Years
|
|
Corrected |
250 |
4383 |
12,865 |
34,500 |
0.007 |
36,500 |
12,865
|
|
Corrected |
375 |
141 |
414 |
34,600 |
0.011 |
23,635 |
13,279
|
|
Corrected |
500 |
816 |
2,395 |
34,600 |
0.014 |
23,221 |
15,674
|
|
Corrected |
700 |
67 |
197 |
34,600 |
0.020 |
20,826 |
15,871
|
|
Corrected |
1500 |
1407 |
4,130 |
34,700 |
0.043 |
20,629 |
20,001
|
|
Corrected |
2500 |
914 |
2,683 |
34,900 |
0.072 |
16,499 |
22,684
|
|
As Read |
4000 |
769 |
2,257 |
35,100 |
0.114 |
13,816 |
24,941
|
|
" " |
5000 |
577 |
1,694 |
35,200 |
0.142 |
11,559 |
26,635
|
|
" " |
6000 |
416 |
1,221 |
35,300 |
0.170 |
9,865 |
27,856
|
|
" " |
7000 |
347 |
1,019 |
35,500 |
0.197 |
8,644 |
28,874
|
|
" " |
8000 |
329 |
966 |
35,600 |
0.225 |
7,626 |
29,840
|
|
" " |
9000 |
251 |
737 |
35,800 |
0.251 |
6,660 |
30,577
|
|
" " |
10000 |
196 |
575 |
35,900 |
0.279 |
5,923 |
31,152
|
|
" " |
11000 |
188 |
552 |
36,000 |
0.306 |
5,348 |
31,704
|
|
" " |
12000 |
160 |
470 |
36,200 |
0.331 |
4,796 |
32,173
|
|
" " |
13000 |
116 |
340 |
36,300 |
0.358 |
4,327 |
32,514
|
|
" " |
14000 |
140 |
411 |
36,500 |
0.384 |
3,986 |
32,925
|
|
" " |
15000 |
107 |
314 |
36,600 |
0.410 |
3,575 |
33,239
|
|
" " |
16000 |
105 |
308 |
36,800 |
0.435 |
3,261 |
33,547
|
|
" " |
17000 |
70 |
205 |
36,900 |
0.461 |
2,953 |
33,753
|
|
" " |
18000 |
65 |
191 |
37,000 |
0.486 |
2,747 |
33,943
|
|
" " |
19000 |
68 |
200 |
37,200 |
0.511 |
2,557 |
34,143
|
|
" " |
20000 |
64 |
188 |
37,300 |
0.536 |
2,357 |
34,331
|
|
" " |
21000 |
69 |
203 |
37,500 |
0.560 |
2,169 |
34,533
|
|
" " |
22000 |
62 |
182 |
37,600 |
0.585 |
1,967 |
34,715
|
|
" " |
23000 |
63 |
185 |
37,700 |
0.610 |
1,785 |
34,900
|
|
" " |
24000 |
59 |
173 |
37,900 |
0.633 |
1,600 |
35,073
|
|
" " |
25000 |
51 |
150 |
38,000 |
0.658 |
1,427 |
35,223
|
|
" " |
26000 |
29 |
85 |
38,200 |
0.681 |
1,277 |
35,308
|
|
" " |
27000 |
59 |
173 |
38,300 |
0.705 |
1,192 |
35,481
|
|
" " |
28000 |
13 |
38 |
38,400 |
0.729 |
1,019 |
35,520
|
|
" " |
29000 |
39 |
114 |
38,600 |
0.751 |
980 |
35,634
|
|
" " |
30000 |
28 |
82 |
38,700 |
0.775 |
866 |
35,716
|
|
" " |
31000 |
18 |
53 |
38,900 |
0.797 |
784 |
35,769
|
|
" " |
32000 |
19 |
56 |
39,000 |
0.821 |
731 |
35,825
|
|
" " |
33000 |
24 |
70 |
39,100 |
0.844 |
675 |
35,895
|
|
" " |
34000 |
22 |
65 |
39,300 |
0.865 |
605 |
35,960
|
|
" " |
35000 |
32 |
94 |
39,400 |
0.888 |
540 |
36,054
|
|
" " |
36000 |
12 |
35 |
39,600 |
0.909 |
446 |
36,089
|
|
" " |
37000 |
14 |
41 |
39,700 |
0.932 |
411 |
36,130
|
|
" " |
38000 |
12 |
35 |
39,800 |
0.955 |
370 |
36,165
|
|
" " |
39000 |
16 |
47 |
40,000 |
0.975 |
335 |
36,212
|
|
" " |
40000 |
14 |
41 |
40,100 |
0.998 |
288 |
36,253
|
|
" " |
41000 |
8 |
23 |
40,300 |
1.017 |
247 |
36,277
|
|
" " |
42000 |
4 |
12 |
40,400 |
1.040 |
223 |
36,289
|
|
" " |
43000 |
8 |
23 |
40,600 |
1.059 |
211 |
36,312
|
|
" " |
44000 |
4 |
12 |
40,700 |
1.081 |
188 |
36,324
|
|
" " |
45000 |
13 |
38 |
40,800 |
1.103 |
176 |
36,362
|
|
" " |
46000 |
11 |
32 |
41,000 |
1.122 |
138 |
36,394
|
|
" " |
47000 |
10 |
29 |
41,100 |
1.144 |
106 |
36,424
|
|
" " |
48000 |
4 |
12 |
41,300 |
1.162 |
76 |
36,435
|
|
" " |
50000 |
6 |
18 |
41,500 |
1.205 |
65 |
36,453
|
|
" " |
60000 |
4 |
12 |
42,900 |
1.399 |
47 |
36,465
|
|
" " |
70000 |
3 |
9 |
44,400 |
1.577 |
35 |
36,474
|
|
" " |
80000 |
4 |
12 |
45,800 |
1.747 |
26 |
36,485
|
|
" " |
100000 |
1 |
3 |
48,600 |
2.058 |
15 |
36,488
|
|
" " |
110000 |
1 |
3 |
50,000 |
2.200 |
12 |
36,491
|
|
" " |
120000 |
1 |
3 |
51,400 |
2.335 |
9 |
36,494
|
|
" " |
130000 |
2 |
6 |
52,800 |
2.462 |
6 |
36,500
|
|
|
|
|
|
|
|
|
|
|
12,435 |
36500 |
|
|
|
|



The Diagram below shows threshold
velocities of sediment in stream flow. The upper curve shows the
velocity necessary for a stream to pick up and move a particle of a
given size. This is a zone on the graph, not a line because of
variations resulting from stream depth, etc. The lower curve
indicated the velocity at which a particle of a given size will
settle out and be deposited. Note that fine particles will stay in
suspension at velocities much lower than those required to lift them
from the stream bed surface.

|