|
ANSWER TO U.S. CORPS OF
ENGINEERS CONCERN NUMBER 2
Reservoir operation required with this plan would
also likely aggravate downstream bank caving.
In
1997, the Corps issued a plan to regulate the reservoir to reduce
downstream bank caving. This plan, actually a list of parameters,
was implemented during a January 1999 minor flood with the result
that the reservoir was depleted to its lowest level in over 11
years. This happened because the parameters conflicted with each
other and people implementing the plan did not know what to do. One
person with the Corps must have understood how to properly do this.
He contributed parameter #16 on page 22 of the plan. In a minor
flood, you must initiate regulation for bank caving when the
reservoir has been prereleased to its minimum pool and you must
control downstream flow with the reservoir rising.
Once everyone understands this,
bank caving procedures will work well and they will actually
complement efforts to prevent damage in major floods by requiring
the people regulating the reservoir to learn how to prerelease in
advance of minor storms. These storms could turn into major storms.
Regulating the reservoir to minimize flooding during major storms
does not conflict with bank caving procedures. The only difference
is that the lake will be at extreme heights at the end of a major
storm and regulation for bank caving will occur with the reservoir
falling.
The following is a summary of the
parameters used for the optimized alternative. Pool limits are shown
in Figure 19:
1. Winter Pool
Stage = 296.0 2. Winter Pool Stage Upper Limit
= 296.4 3. Winter Pool Stage Bank Caving Lower
Limit = 295.8 until April 1, increasing gradually to 296.0 on
May 4. Winter Pool Stage Prerelease Lower
Limit = 295.0 (292.0 for extreme events) 5.
Recreation Pool Stage = 297.4 6. Recreation
Pool Stage Upper Limit = 297.7 7. Recreation
Pool Stage Lower Limit for Bank Caving = ranges from 297.4 on
June 1st to 296.9 on November 1st. 8.
Recreation Pool Stage Prerelease Lower Limit = 296.0 (292.0
for extreme events) 9. Maximum Daily Drop in
Reservoir due to Evacuation = 0.50 feet 10. Minimum Outflow
= 375 cfs 11. Minimum Forcasted Inflow Before Prereleasing
= 30,000 cfs 12. Number of days ahead to forecast = 2
days 13. Flood Control Stage Table:
|
Flow |
Flood Control
Stage |
| 30,000 - 40,000
cfs |
296.7
(297.6 rec. pool) |
| 40,000 - 50,000
cfs |
297.0
(297.6 rec. pool) |
| 50,000 - 75,000
cfs |
297.6 |
| 75,000 - 100,000
cfs |
299.5 |
| over 100,000
cfs |
299.8 |
14. Targeted Daily Rate of Fall
of Jackson Gage for Bank Caving = 2.0 feet 15. Maximum
Stage at which to Consider Bank Caving = 28.00 feet 16.
Maximum Daily Rise in Reservoir for Storage for Bank Caving =
0.50 feet
Figure 19. Ross Barnett
Pool Operation - Optimized Alternative

BANK SLOUGHING
PROCEDURE
For a minor
flood event (one that does not require use of the reservoir's
cajpacity to prevent flood damage) the reservoir should be
pre-released (based on rainfall and stream flow data) to its minimum
winter pool level (295.8') in the early stages of the flood event.
This level should be maintained until approximately 8-1/2 billion
cubic feet of runoff remains in the watershed. This will occur when
the reservoir inflow equals 25,000 cfs.
Watershed
"run-out" that provides inflow to the reservoir in the last stages
of a flood event follows a very consistent pattern. Six floods were
measured to determine the amount of "run-out" that occurred after
reservoir inflows had decreased to 25,000 cubic feet per second.
Notice how consistent the results are in the table below:
| Inflow (Thousand cubic
feet/second) |
|
|
|
|
|
|
|
| Day |
1969 |
1976 |
1977 |
1979 |
1980 |
1983 |
|
|
|
|
|
|
|
|
1 |
25 |
25 |
25 |
25 |
25 |
25 |
|
2 |
20 |
20 |
20 |
20 |
20 |
22 |
|
3 |
16 |
15 |
15 |
16 |
15 |
17 |
|
4 |
10 |
10 |
10 |
15 |
10 |
10 |
|
5 |
7 |
8 |
7 |
6 |
8 |
6 |
|
6 |
5 |
7 |
6 |
4 |
7 |
5 |
|
7 |
4 |
5 |
3 |
3 |
5 |
3 |
|
8 |
3 |
3 |
3 |
3 |
3 |
3 |
|
9 |
2 |
2 |
3 |
2 |
3 |
2 |
| 10 |
1 |
1 |
2 |
2 |
2 |
2 |
| BCF |
8.0 |
8.3 |
8.1 |
8.3 |
8.4 |
8.2 |
The
following procedure will prevent fall opposite downstream channel
banks from exceeding two feet per day. The procedure should be
instigated when reservoir "in flow" has declined to 25,000 cubic
feet per second.
| Day |
Discharge |
|
|
| 1 |
18 |
| 2 |
15 |
| 3 |
12 |
| 4 |
10 |
| 5 |
9 |
| 6 |
8 |
| 7 |
7 |
| 8 |
6 |
| 9 |
5 |
| 10 |
4 |
| 11 |
3 |
| 12 |
2 |
| 13 |
1 |
|
8.6
BCF |
Following
this procedure will require 8.6 billion cubic feet of water.
Initiating the procedure when the watershed has not "run out" and
approximately 8-1/2 billion cubic feet remain in it assures that the
procedure will not run out of water. The procedures require that the
reservoir cut discharge back to 18,000 cfc when the inflow is at
25,000 cfs. This results in a filling of the reservoir during the
initial phase of the procedure. For this reason it is necessary to
begin the procedure with the reservoir at minimum pool (295.8') to
allow room for the reservoir rise.
Following
this rocedure, the reesrvoir should respond approximate, according
to the following schedule:
| Day |
Reservoir Level |
Inflow CFS |
Discharge CFS |
Net Reservoir Change CFS |
Jackson Gauge |
| Begin |
End |
|
|
|
|
|
|
|
|
1 |
295.8 |
25 |
16 |
+9 |
32' |
28' |
|
2 |
|
20 |
14 |
+6 |
|
27' |
|
3 |
|
15.5 |
12 |
+3.5 |
|
25' |
|
4 |
|
11 |
10 |
+1 |
|
24' |
|
5 |
297.0 |
7 |
9 |
-2 |
|
22' |
|
6 |
|
6 |
8 |
-2 |
|
21' |
|
7 |
|
3.5 |
7 |
-3.5 |
|
19' |
|
8 |
|
3 |
6 |
-3 |
|
17' |
|
9 |
|
2.5 |
5 |
-2.5 |
|
15' |
| 10 |
|
2 |
4 |
-2 |
|
13' |
| 11 |
|
1.5 |
3 |
-1.5 |
|
11' |
| 12 |
|
1 |
2 |
-2 |
|
10' |
| 13 |
295.9 |
1 |
1 |
|
|
|
|
|
8.5 BGF |
8.3 BCF |
|
|
|
After a
major flood event, the reservoir will be in the process of being
"let down" form extreme elevations. The bank sloughing pocedure
should be initiated when the combined volumes of water form two
sources equal 8.5 billion cubic feet. These sources are:
-
The capacity of the reservoir
that existes above minimum pool
-
The "run-off" remaining in the
watershed
Example: The reservoir has been
let down to a level of 297.8' when inflow has dropped to 25,000
cubic feet of water per second.
-
Capacity of the reservoir form
297.8' to 295.8' equals 2.8 billion cubic feet
-
Capacity of the watershed equals
8.5 BCF
-
The total available for discharge
is 11.3 BCF
In this instance, continue
discharging at a "let-down" rate until the two sums add up to
8.5 BCF. Remember that these two valves are extremely
dependable.
Example:
Continued discharge at 30,000 CFS for 24 hours will lower the
reservoir approximately 05 feet to 297.3'. also, during this time
approximately 2.0 BCF will have flowed out f the watershed. This
would leave approximately 2.0 BCF of capacity in the reservoir above
minimum pool and 6.5 BCF of "run-out" left in the watershed. Bank
sloughing should be initiated at this time.
Following
this procedure, the reservoir should respond approximately,
according to the following schedule:
| Day |
Reservoir Level |
Inflow CFS |
Discharge CFS |
Net Reservoir Change CFS |
Jackson Gauge |
| Begin |
End |
|
|
|
|
|
|
|
|
1 |
297.3 |
20 |
16 |
+4 |
32' |
28 |
|
2 |
|
15.5 |
14 |
+1.5 |
|
27 |
|
3 |
297.6 |
11 |
12 |
-1 |
|
25 |
|
4 |
|
7 |
10 |
-3 |
|
24 |
|
5 |
|
6 |
9 |
-3 |
|
22 |
|
6 |
|
3.5 |
8 |
-4.5 |
|
21 |
|
7 |
|
3 |
7 |
-4 |
|
19 |
|
8 |
|
2.5 |
6 |
-3.5 |
|
17 |
|
9 |
|
2 |
5 |
-3 |
|
15 |
| 10 |
|
1.5 |
4 |
-2.5 |
|
13 |
| 11 |
|
1 |
3 |
-2 |
|
11 |
| 12 |
|
1 |
2 |
-1 |
|
10 |
| 13 |
295.9 |
1 |
1 |
---- |
|
9 |
This
procedure is not intended to be exact. It describes a principal to
be utilized that will affect a 2' minimum fall in the channel below
the reservoir. The procedure can be refined with more study and
adjustments to discharge can be made thoughour the procedure as
indicated by inflow.

The
Jackson lake weirs automatically regulate steady flow. They prevent
sudden rate changes. This would assist the reservoir in regulating
for downstream bank sloughing. The following is a chart which shows
reservoir discharge and the corresponding discharge that will pass
the weir. If the reservoir were to suddenly increase discharge from
20,000 cubic feet per second to 80,000 cubic feet per second and
hold this rate for six hours, the reservoir would drop one foot in
elevation. The column on the right side of the charge shows that the
discharge over the weir would increase gradually over six hours
until it reached a rate of 74,000 cubic feet per second downstream.
If the discharge were just as suddently cut back from 80,000 cubic
feet per second to 20,000 cubic feet per second, the weir would
cause the lower lake to fall gradually. It would require over ten
hours for the flow over the weirs to return to the 20,000 cubic feet
per second rate. The chart is shown to demonstrate what the weir
could do in an emergency. The plan does not call for making such
sudden changes in the discharge rate at the reservoir.
| HOUR |
RESERVOIR DISCHARGE |
AVERAGE LAKE
LEVEL |
LAKE LEVEL AT
WEIR |
FLOW RATE AT
WEIR |
| 1 |
20000 |
271.1 |
271.0 |
20000 |
| 2 |
20000 |
271.1 |
271.0 |
20000 |
| 3 |
80000 |
272.0 |
271.4 |
28000 |
| 4 |
80000 |
272.6 |
272.0 |
44000 |
| 5 |
80000 |
273.1 |
272.5 |
56000 |
| 6 |
80000 |
273.4 |
272.8 |
65000 |
| 7 |
80000 |
273.5 |
272.9 |
70000 |
| 8 |
80000 |
273.6 |
273.1 |
74000 |
| 9 |
20000 |
272.8 |
272.8 |
66000 |
| 10 |
20000 |
272.3 |
272.2 |
50000 |
| 11 |
20000 |
271.9 |
271.9 |
40000 |
| 12 |
20000 |
271.7 |
271.6 |
34000 |
| 13 |
20000 |
271.5 |
271.5 |
30000 |
| 14 |
20000 |
271.4 |
271.3 |
27000 |
| 15 |
20000 |
271.3 |
271.2 |
25000 |
| 16 |
20000 |
271.2 |
271.2 |
24000 |
| 17 |
20000 |
271.2 |
271.1 |
23000 |
| 18 |
20000 |
271.1 |
271.1 |
22000 |
| 19 |
20000 |
271.1 |
271.1 |
21000 |
| 20 |
20000 |
271.1 |
271.1 |
21000 |
| 21 |
20000 |
271.1 |
271.0 |
21000 |
| 22 |
20000 |
271.1 |
271.0 |
20000 |
| 23 |
20000 |
271.1 |
271.0 |
20000 |
| 24 |
20000 |
271.1 |
271.0 |
20000 |
THESE FLOWRATES WOULD LOWER
THE RESERVOIR ONE FOOT (1.3 BILLION CUBIC FEET) IN
SIX HOURS ASSUMING AN AVERAGE INFLOW OF 20000
CFS. |