The Importance of Regulating the Discharge of the Reservoir
at
the End of a Heavy Rainfall Period
It has been established that the banks of the Pearl River below the Ross
Barnett Reservoir Dam have had increasing instances of sloughing (cave-in) since
the reservoir has been in operation. (Note that this sloughing is in addition to
the normal sloughing and erosion that is a part of any river)
One of the prime causes of bank sloughing is river bank saturation by a high
river level, and a subsequent rapid drop of the river. This saturation will
occur quickly when the river overflows the bank. If the drop of the river is
faster than the water can flow out of the bank, a pressure imbalance is created,
and failure can occur. Reservoir operation has the capability of both aggravating
or reducing this condition.
Bank sloughing continues to threaten structures that lie along the banks of
the river today, as an example, a bridge near Monticello is to be re-located (at
a cost of two million dollars) because of bank sloughing on a straight portion
of the Pearl River. Adjacent to the bridge, numerous structures are in danger of
falling into the Pearl.
The Corps of Engineers has an established that if the drawdown rate is two
feet per day or less, bank sloughing is greatly reduced. The Corps also noted
that falls greater than two feet per day were much more common after the
reservoir was built. This increases the occurrences of bank sloughing downstream. Their recommendation
is that the reservoir control the
rate of flow decrease so that the fall is limited to two feet per day at the
highway 80 gauge. This allows time for the water to seep from the bank,
decreasing the pressure that causes the bank to slough. This recommendation is
to take effect when the highway 80 gauge has reached 28 feet, a level at which
the river has overflowed the banks.
The
Corps blamed the increased occurrences of high drawdown rates on lack
of rainfall absorption in the land occupied by the lake, channel
improvements upstream, and increased development around the
reservoir. However, upon formulation, we are unable to find
these courses to be significant. The Two Lake Foundation believes
that the dominant reason for the change is that the reservoir
eliminated 30 miles of river reach and adjacent flatwoods, which served
to store water during floods and slowly let it back in as the river
fell. Keeping the reservoir at a constant level eliminates this
beneficial process.
The following graph shows the complete cycle of rise and fall during the
April 2000 rain event. Note the rapid falls at each location, which is primarily
due to a sharp decrease in flow from the reservoir.

As can be seen in the above graph, the highway 80 gauge experienced a rate of
fall of ten feet over a 48 hour period, clearly in excess of the two
foot per day maximum, and at the expense of downstream communities. It is
possible that the reservoir, which experienced very low levels last year because
of abnormally dry weather, has decreased emphasis on sloughing to assure that
sufficient water is available in the reservoir for recreation.
The Two Lake Plan has developed a sloughing procedure (based on the Corps
guidelines), that will both maintain a desired reservoir water level, and prevent
a rapid fall and subsequent sloughing of river banks downstream of Jackson. The
following graph also shows how a two foot per day fall could have been achieved
without danger of leaving the reservoir too low at the end of the procedure.

Sloughing Results for February 1999
In February 1999, the reservoir performed a sloughing operation by
maintaining an almost constant rate of discharge decrease as shown in the graph
below. Note the shape of the fall at highway 80. Since the stage is not directly
related to the rate of discharge, it has a curved shape, which caused a fall of
greater than two feet per day to occur.

The next chart shows the same time period, and how the reservoir also dropped too
low at the end of the procedure. This could have been prevented with the Two
Lake sloughing plan. The low water level at the end of the procedure was an
unfortunate start to the very dry season that followed, where the reservoir
never recovered to the normal level. The Two Lake plan could have added a foot
or more to the water level at the end of the procedure, which would have kept
the water at safe levels for longer during that dry season. The failure on
the part of the reservoir to successfully apply this procedure in February 1999
could be the reason that they did not try to do it in April 2000.

Sloughing Results for April 2000
The following graph shows the rate of fall after the April 2000
rain event, and how the Two Lake procedure differs. Note that the highway 80
stage with Two Lake sloughing is a straight line with a fall of two feet per
day. This is achieved by a sloughing discharge that releases a greater volume at
the start of the procedure than at the end. The accuracy of inflow
projections along with the ability to make changes during this procedure should
give results fairly close to these projected results. The basic principle
of the Two Lake sloughing plan is simple:
-To perform the procedure requires about 8.5 billion cubic
feet (BCF) of water
-To the 8.5 BCF, add or subtract the volume required
for any desired change to reservoir
level
-When the reservoir watershed has target volume of
water remaining, start the procedure.
Note that 8.5 billion cubic feet has an allowance for
errors.

Need for an Independent Specialist to Regulate the Reservoir
(Only during and immediately after large rain events)
The Two Lake Foundation has proposed that a specialist be retained with a
demonstrated ability in flood control and reservoir volume management. Unique conditions
control the interaction between the reservoir, the Jackson
metropolitan area, and the downstream communities. This makes the solving
of Jackson's flooding situation into a "custom" job which does not lend itself
well to solutions on generalized computer programs such as that used by the
Corps, or national/international engineering firms. For this reason, the
Two Lakes Foundation believes that a local person, whose prime interests are:
-The reduction of flooding in all communities below
the reservoir
-The reduction in bank cave-ins below the reservoir
-The maintenance of normal reservoir water levels
except in extreme conditions
This person should have
independent control over the functions of the reservoir during times of
significant rainfall. This specialist would also assure that accurate
rainfall and streamflow data are available to make the timely assessments during
a rain event, and to be able to react in a
timely manner. That person would openly communicate the status and actions
to all parties by publishing it
to the internet. It is critical that this person be free from all constraints,
and provide reservoir regulation that would be in the best interest of both all
parties.
Those responsible for regulation of the reservoir might argue that the plan
offered by the Two Lake Foundation would cause extreme fluctuations in reservoir
levels. The Two Lake Foundation has shown that reservoir regulation does not
have to be at the expense of those living on, or using the reservoir.